Free PMI Project Management Professional (PMP) Practice Question
The project schedule should be consistently revised throughout the project lifecycle to accommodate changes in project scope and resource availability.
The correct answer is True. In project management, especially in methodologies that involve iterative and incremental practices, the project schedule needs to accommodate adjustments due to changes in project scope, resource availability, and other influencing factors. This ensures that the project aligns with client needs and handles any unforeseen changes effectively, maintaining the project's viability and business value.
Learn More
AI Generated Content may display inaccurate information, always double-check anything important.
Why is it important to revise the project schedule?
What are some common reasons for changes in project scope?
What methodologies support the need for schedule revisions?