True or False: If an activity has an Early Start (ES) of day 10, Early Finish (EF) of day 20, Late Start (LS) of day 12, and Late Finish (LF) of day 22, the float for this activity is 2 days.
This statement is True. Float is calculated as either LS - ES or LF - EF. Using both formulas, Float = LS - ES = 12 - 10 = 2 days and Float = LF - EF = 22 - 20 = 2 days. Therefore, the float for this activity is indeed 2 days.