True or False: If an activity has an Early Start (ES) of day 10, Early Finish (EF) of day 20, Late Start (LS) of day 12, and Late Finish (LF) of day 22, the float for this activity is 2 days.
This statement is True. Float is calculated as either LS - ES or LF - EF. Using both formulas, Float = LS - ES = 12 - 10 = 2 days and Float = LF - EF = 22 - 20 = 2 days. Therefore, the float for this activity is indeed 2 days.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is float in project management?
Open an interactive chat with Bash
How do you calculate float?
Open an interactive chat with Bash
What are Early Start and Late Start in project management?
Open an interactive chat with Bash
This question's topic:
PMI Project Management Professional (PMP) /
People
Report Issue
Oh snap!
Loading...
Loading...
Join premium for unlimited access and more features