Free PMI Project Management Professional (PMP) Practice Question

Using PERT, if the optimistic time estimate is 4 days, the pessimistic time estimate is 12 days, and the most likely time estimate is 6 days, the expected duration of the activity is 6 days.

  • False

  • True

This question's topic:
PMI Project Management Professional (PMP) / 
People
Your Score:

Check or uncheck an objective to set which questions you will receive.