What best describes a situation where a project manager should use a directive leadership style?
When the project is not time-sensitive and the team is self-motivated
When the team lacks knowledge and the task requires immediate completion
When the manager wants to boost team creativity during brainstorming sessions
When the team is highly experienced and the task is complex