Free PMI Project Management Professional (PMP) Practice Question

What is a primary method for empowering project team members to take ownership of their assignments?

  • Conduct regular team-building exercises

  • Involve them in the project planning and estimation process

  • Offer additional certification opportunities

  • Provide conflict resolution training

This question's topic:
PMI Project Management Professional (PMP) / 
People
Your Score:

Check or uncheck an objective to set which questions you will receive.