Free PMI Project Management Professional (PMP) Practice Question

What is the BEST step a project manager should take when a key stakeholder submits a change request that could significantly affect the project's schedule but might offer considerable benefits if incorporated?

  • Reject the change request to avoid any impact on the project's schedule

  • Present the change request to the change control board (CCB) for review and decision

  • Conduct a review and approve or reject accordingly

  • Implement the change to take advantage of the benefits

This question's topic:
PMI Project Management Professional (PMP) / 
Waterfall
Your Score:

Check or uncheck an objective to set which questions you will receive.