What is the BEST step a project manager should take when a key stakeholder submits a change request that could significantly affect the project's schedule but might offer considerable benefits if incorporated?
Reject the change request to avoid any impact on the project's schedule
Present the change request to the change control board (CCB) for review and decision
Conduct a review and approve or reject accordingly
Implement the change to take advantage of the benefits