Free PMI Project Management Professional (PMP) Practice Question

What is the expected outcome when an Agile team conducts a retrospective?

  • To produce a detailed plan for the entire project going forward

  • To document team disagreements and solutions for future legal reference

  • To allocate blame for project challenges and failures experienced in the last iteration

  • To collaborate on identifying areas for process and product improvement based on the previous work

This question's topic:
PMI Project Management Professional (PMP) / 
Agile
Your Score:

Check or uncheck an objective to set which questions you will receive.