What is the first step a project manager should take to aid in the successful implementation of project deliverables that require changes to the organizational culture?

  • Launch an organizational publicity campaign to promote the benefits of the project

  • Encourage key organizational members resistant to change to encourage buy-in

  • Redesign organizational structure to align with the proposed changes

  • Analyze the existing organizational culture for values, norms, and behaviors