What is the main objective of categorizing risks within the framework of project risk management?

  • To document the risk management process in accordance with compliance and regulatory requirements

  • To assign specific risk owners to each identified risk based on their potential impact on the project scope

  • To determine and prioritize the project areas most exposed to effects of uncertainty, and to focus risk management efforts appropriately

  • To calculate the precise financial impact of each risk on the project budget