What is the main purpose of establishing an appropriate governance structure for a project?
To allow the project team complete freedom in managing the project without the need to adhere to external controls.
To create an entirely new set of governance standards specific to each project, independent of organizational policies.
To focus on the technical aspects of the project, ignoring the organizational governance standards.
To align the project with the organization's governance standards and maintain control over decision-making processes.