What is the most appropriate initial step in determining how to address and manage compliance needs for a new project?

  • Measure current compliance levels against industry standards

  • Classify the project's deliverables according to their importance for compliance

  • Identify all applicable compliance requirements for the project

  • Develop a risk management plan to mitigate potential compliance threats