What is the primary function of establishing escalation paths and thresholds within a project governance structure?
To track the performance of team members and manage evaluations
To reduce the overall risks associated with the project by involving senior management
To ensure that issues are addressed by the appropriate level of management at the correct time
To directly resolve resource constraints and allocate additional resources effectively