What is the primary goal of creating a Risk Response Plan in project management?
To outline strategies and actions to manage identified risks and ensure the project remains within its risk thresholds
To allocate a risk budget progressively throughout the project as risks are identified
To compile a list of risk responses in a chronological log for implementation after the project has concluded
To document important risks and retain them for historical records and analysis