Free PMI Project Management Professional (PMP) Practice Question

What is the primary purpose of evaluating the engagement needs of stakeholders in a project?

  • To determine the technical skills of the stakeholders

  • To document detailed project deliverables required by each stakeholder

  • To understand the stakeholder's expectations and tailor communication accordingly

  • To analyze the financial impact stakeholders have on the project