What is the primary purpose of validating readiness for transition in project management?

  • To identify new risks and issues that may arise in the next phase

  • To secure additional funding for the next phase of the project

  • To update the project schedule with new milestones for the next phase

  • To ensure all necessary deliverables and knowledge transfer are completed for a smooth handover