What is the primary purpose of validating readiness for transition in project management?
To secure additional funding for the next phase of the project
To update the project schedule with new milestones for the next phase
To identify new risks and issues that may arise in the next phase
To ensure all necessary deliverables and knowledge transfer are completed for a smooth handover