What is the primary purpose of validating readiness for transition in project management?
To identify new risks and issues that may arise in the next phase
To ensure all necessary deliverables and knowledge transfer are completed for a smooth handover
To update the project schedule with new milestones for the next phase
To secure additional funding for the next phase of the project