What is the principal purpose of applying the Delphi Technique during the risk identification process?
To collect expert risk assessments anonymously and reach a consensus on project risks without dominance bias.
To focus on task assignments based on strong recommendations from subject matter experts in the field of risk management.
To involve all project stakeholders in creating a thorough project plan aimed at addressing identified risks comprehensively.
To establish a list of project activities, highlighting those identified as vital by expert evaluation.