What is the principal purpose of applying the Delphi Technique during the risk identification process?
To establish a list of project activities, highlighting those identified as vital by expert evaluation.
To collect expert risk assessments anonymously and reach a consensus on project risks without dominance bias.
To involve all project stakeholders in creating a thorough project plan aimed at addressing identified risks comprehensively.
To focus on task assignments based on strong recommendations from subject matter experts in the field of risk management.