What is the purpose of consolidating project plans during the integration of project planning activities?

  • To identify dependencies, gaps, and potential conflicts between project plans

  • To review each plan individually for completeness and accuracy

  • To communicate the consolidated plans to all stakeholders

  • To obtain formal approval for the consolidated project plans