What practice is most effective for ensuring stakeholder needs and project objectives are in sync and achieving success in the project's deliverables?
Frequent auditing of stakeholder activities
Keeping information about the project confidential from stakeholders
Setting strict deadlines for stakeholder decisions
Establishing open communication channels