Free PMI Project Management Professional (PMP) Practice Question

What type of risk analysis activity brings project team members and stakeholders together in a structured setting to identify project risks collaboratively?

  • Risk Categorization

  • Risk Reassessment

  • Risk Audit

  • Risk Workshop