Free PMI Project Management Professional (PMP) Practice Question

When a change request is approved, what should the project manager do next to ensure the project continues to progress?

  • Conduct a risk assessment of the approved change

  • Submit another change request to refine the approved change

  • Confirm the change has been implemented and retroactively update the project plan

  • Update the project management plan and communicate the change to stakeholders

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.