When a significant change in project scope is identified, which of the following actions should a project manager take to best align with change management practices?

  • Review the change request in detail with the change control board (CCB) for assessment and decision making.

  • Prioritize the new scope change over other project tasks to quickly incorporate the change into the project.

  • Consult with individual team members to obtain their input and proceed with adjustments based on their expertise.

  • Update the project management plan to reflect the new change, ensuring that the project remains up to date.