When consolidating project plans, what is the BEST approach to ensure the plans are integrated effectively?

  • Determine the critical information needed to execute the consolidated plans

  • Combine all the individual plans into a single master plan using a project management system as most PM systems will alert the project manager of red flags or issues

  • Analyze the consolidated project plans for dependencies, gaps, and continued business value

  • Assess the consolidated plans for potential risks