When developing risk responses, what are the primary strategies used to address threats that may negatively impact project objectives?
Accept, Enhance, Share, Transfer
Exploit, Transfer, Accept, Mitigate
Share, Escalate, Enhance, Avoid
Avoid, Transfer, Mitigate, Accept, Escalate