When establishing the requirements for managing project artifacts on a new project, which of the following would best ensure that these artifacts are maintained accurately and are easily accessible to stakeholders?
Establish a centralized repository with version control and defined access permissions for stakeholders.
Implement an offsite backup for all project artifacts as the means of managing them.
Send out frequent reminders to the project team about where artifacts should be stored.
Instruct the project team to memorize the physical and digital locations of all project artifacts.