Free PMI Project Management Professional (PMP) Practice Question

When planning a project schedule, which of the following is the most effective way to improve the accuracy of task duration estimates?

  • Rely solely on the expert judgment of the project manager

  • Utilize benchmarks and historical data from similar past projects

  • Ask each team member to provide their own estimates without any guidance

  • Add arbitrary time buffers to each task duration

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.