When planning a project schedule, which of the following is the most effective way to improve the accuracy of task duration estimates?
Rely solely on the expert judgment of the project manager
Utilize benchmarks and historical data from similar past projects
Ask each team member to provide their own estimates without any guidance
Add arbitrary time buffers to each task duration