Which condition unequivocally categorizes a previously identified project risk as an issue?
When stakeholders express increased concern about potential risks.
When it is first identified during a risk assessment meeting.
When the probability of the risk occurring becomes higher in forecasts.
When the risk materializes and impacts the project deliverables or timelines.