Free PMI Project Management Professional (PMP) Practice Question

Which of the following activities is most crucial to perform when closing out a project phase to ensure value for future projects?

  • Discussing project responsibilities within the team for the next phase

  • Conducting a retrospective meeting to document lessons learned

  • Releasing project resources back to the resource pool

  • Updating procurement financials to reflect final costs

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score: