Free PMI Project Management Professional (PMP) Practice Question

Which of the following approaches is BEST for a project manager to support the team in subdividing project tasks to identify the minimum viable product?

  • Using user stories to map out requirements for each functional need

  • Implementing a comprehensive quality assurance plan at the start of the project

  • Developing a detailed timeline for the project's entire duration

  • Creating an organizational chart to outline project responsibilities

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.