Which of the following approaches is BEST for a project manager to support the team in subdividing project tasks to identify the minimum viable product?
Using user stories to map out requirements for each functional need
Implementing a comprehensive quality assurance plan at the start of the project
Developing a detailed timeline for the project's entire duration
Creating an organizational chart to outline project responsibilities