Which of the following approaches is BEST for a project manager to support the team in subdividing project tasks to identify the minimum viable product?
Using user stories to map out requirements for each functional need
Creating an organizational chart to outline project responsibilities
Implementing a comprehensive quality assurance plan at the start of the project
Developing a detailed timeline for the project's entire duration