Which of the following best captures the essence of the Agile Manifesto's view on responding to change?

  • Avoiding changes in project scope at all costs to maintain stability

  • Documenting every change request before considering implementation

  • Prioritizing response to change over strict adherence to a set plan

  • Valuing a well-detailed plan over quickly adapting to changes