Free PMI Project Management Professional (PMP) Practice Question

Which of the following best describes how a project manager should adjust the project schedule when using an agile methodology?

  • Create a detailed schedule at the beginning of the project and strictly adhere to it

  • Update the schedule at the end of each project phase based on actual progress and remaining work

  • Only adjust the schedule if there are significant delays or scope changes approved by the change control board

  • Collaborate with the team to regularly review and update the schedule based on progress and changing priorities

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.