Which of the following best describes how the project schedule is typically prepared in an Agile project methodology?
The team works in short iterations, planning and scheduling work for each iteration separately.
The project sponsor provides a fixed schedule that the team must adhere to throughout the project.
The project schedule is prepared using the critical path method, identifying the longest sequence of tasks.
The project manager creates a detailed Gantt chart with all tasks and dependencies at the beginning of the project.