Free PMI Project Management Professional (PMP) Practice Question

Which of the following best describes how the project schedule is typically prepared in an Agile project methodology?

  • The team works in short iterations, planning and scheduling work for each iteration separately.

  • The project sponsor provides a fixed schedule that the team must adhere to throughout the project.

  • The project schedule is prepared using the critical path method, identifying the longest sequence of tasks.

  • The project manager creates a detailed Gantt chart with all tasks and dependencies at the beginning of the project.

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.