Which of the following is an essential process for understanding and adapting to the influences of external business fluctuations on the project?
Scheduling additional project team meetings to discuss external factors informally
Developing a new project charter for each change in the external environment
Performing a PESTLE analysis to recognize important trends and changes
Increasing the project's contingency reserve to buffer against external changes