Free PMI Project Management Professional (PMP) Practice Question

Which of the following is NOT typically included in a project's procurement strategy?

  • Managing suppliers and contracts throughout the project

  • Defining resource requirements and needs

  • Communicating resource requirements to stakeholders

  • Developing a detailed risk management plan

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.