Free PMI Project Management Professional (PMP) Practice Question

Which of the following is the BEST approach for determining the requirements for managing project artifacts?

  • Assign a team member to be responsible for managing all project artifacts in order to streamline the process

  • Establish a plan at the beginning of the project that defines what, when, where, and who for managing artifacts

  • Update project artifacts as changes occur throughout the project lifecycle

  • Store all project artifacts in a shared repository accessible to the team

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.