Free PMI Project Management Professional (PMP) Practice Question

Which of the following is the BEST example of using iterative and incremental practices throughout the project life cycle?

  • Performing risk assessments during the planning phase

  • Conducting lessons learned sessions at the end of each project phase

  • Updating project documentation sporadically throughout the project

  • Continuously engaging stakeholders and incorporating their feedback

This question's topic:
PMI Project Management Professional (PMP) / 
Process