Which of the following strategies are MOST appropriate for dealing with opportunities according to the Project Risk Management Knowledge Area?
Mitigate, Accept, Transfer, Exploit
Exploit, Share, Enhance, Accept, Escalate
Avoid, Transfer, Mitigate, Accept
Transfer, Mitigate, Share, Escalate