Free PMI Project Management Professional (PMP) Practice Question

Which of the following strategies are MOST appropriate for dealing with opportunities according to the Project Risk Management Knowledge Area?

  • Mitigate, Accept, Transfer, Exploit

  • Exploit, Share, Enhance, Accept, Escalate

  • Avoid, Transfer, Mitigate, Accept

  • Transfer, Mitigate, Share, Escalate

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.