Free PMI Project Management Professional (PMP) Practice Question

Which practice is MOST valuable for a team to ensure consistent delivery of high-quality increments during Agile Project Execution?

  • Planning large releases with extensive features to maximize the value delivered to stakeholders at the end of the project.

  • Focusing primarily on detailed upfront planning to prevent any need for changes during the execution phase.

  • Assigning a gatekeeper to review and approve changes individually to ensure each increment meets the quality standards before integration.

  • Incorporating continuous integration and frequent testing to detect and resolve issues rapidly, sustaining a high level of quality.