While executing a project, you identify that a previously documented risk has occurred, and it is impacting your project schedule. Which of the following actions should you take to address this situation as per the agreed-upon risk response plan?

  • Execute the predefined risk response plan that includes mitigation or contingency actions.

  • Reevaluate the risk response plan for appropriateness.

  • Update the risk register with the details of the risk occurrence.

  • Update the project stakeholders about the risk occurrence and impact.