Free PMI Project Management Professional (PMP) Practice Question

You are finalizing the communications management plan for a project with international stakeholders. These stakeholders have varying time zones, languages, and cultural communication preferences. What would be the most effective approach to manage the distribution of project updates?

  • Distribute weekly status updates via email in the project manager’s preferred language to maintain consistency across all stakeholders.

  • Condense all updates into a detailed monthly report to reduce the frequency of communications and thus simplify the process.

  • Schedule communication at a time that is satisfactory to all key stakeholders, taking into account time zones and cultural differences, and offer translations as required.

  • Establish bi-weekly video conferences at a fixed time convenient to the project manager's location.

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.