You are leading a project that is nearing its completion. As part of the closing process, you must confirm that specific criteria are met to declare the project successfully closed. Which of the following would be an essential element to verify?

  • Stakeholder satisfaction has been reported above 90%.

  • The operational team is ready to assume control over project outputs.

  • The project deliverables have been completed according to the agreed-upon scope.

  • The overall project budget has been underspent by 10%.