Free PMI Project Management Professional (PMP) Practice Question

You are leading a project to develop a new software application. During the planning phase, you realize that the project coincides with multiple other projects, leading to a potential shortage of available software engineers with the necessary skills within your organization. What should you do to ensure adequate resourcing for the project?

  • Conduct a resource leveling exercise to balance demand against available supply.

  • Reschedule the project to align with the availability of software engineers.

  • Perform a detailed skills analysis and create a training plan for existing employees.

  • Increase the project budget to accommodate for hiring additional staff.

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.