Free PMI Project Management Professional (PMP) Practice Question

You are leading the closure of a software development project. Which of the following criteria is MOST crucial to decide whether the project can be successfully closed?

  • All project team members agree that their tasks are complete

  • Final project documentation has been approved by the project sponsor

  • The project has stayed within the allocated budget

  • Confirmation that the software meets all functional and non-functional requirements specified in the project scope

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.