You are managing a complex project and have just completed a major milestone. Upon reviewing the project documentation, you notice that the scope baseline and the actual performance of project work have significant variances. What should be your next action as a project manager to bring the project back on track?

  • Conduct a variance analysis to understand the variance's cause and determine appropriate corrective or preventive actions.

  • Rebaseline the project scope.

  • Adjust the project's quality metrics to accommodate the variances.

  • Take no immediate action, but begin closely observing the next milestone's progress for additional variances.