You are managing a new infrastructure project that has stringent quality requirements due to the potential environmental impacts and safety concerns. Which of the following is the BEST action to take when beginning the process of planning for quality management?

  • Review organizational process assets and the lessons learned repository from previous similar projects.

  • Review the stakeholder register to determine the stakeholders' quality expectations and standards.

  • Begin developing specific quality metrics for each deliverable.

  • Examine the project's cost baseline for its alignment with the expected quality standards.