You are managing a project aimed at enhancing software capabilities to improve operational efficiency. Which step should you take to ensure that all anticipated benefits of the project are thoroughly identified and aligned with organizational goals?

  • Send out client surveys to gauge customer satisfaction with current services.

  • Organize internal team brainstorming sessions

  • Conduct stakeholder interviews to understand their expectations and how they will use the project's outputs.

  • Analyze industry benchmarks and competitor analysis reports.

This question's topic:
PMI Project Management Professional (PMP) / 
Business Environment