You are managing a project that involves multiple stakeholders. After several negotiation sessions, you have reached a consensus on the project's scope and deliverables. What should you do next to support the outcome of the parties' agreement?

  • Rely on the key stakeholders' memory of the agreement to avoid bureaucracy and save time.

  • Document the agreement and share it with all relevant parties.

  • Begin work on the project tasks as per the verbal agreement to maintain momentum.

  • Inform the team members about the agreement in the next meeting.