Free PMI Project Management Professional (PMP) Practice Question

You are managing a project under a fixed-price incentive fee contract with a ceiling price of $1,200,000, a target cost of $1,000,000, and a target price of $1,100,000. If the buyer's share ratio is 80/20, what is the Point of Total Assumption (PTA)?

  • $1,000,000

  • $1,500,000

  • $1,025,000

  • $1,125,000

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.