Free PMI Project Management Professional (PMP) Practice Question

You are managing a project with a Budget at Completion (BAC) of $1,200,000. As of the last reporting period, the Earned Value (EV) is $400,000 and the Actual Costs (AC) are $500,000. Assuming that the project will continue to perform at the same Cost Performance Index (CPI), what is the Estimate at Completion (EAC)?

  • $1,400,000

  • $1,200,000

  • $1,100,000

  • $1,500,000

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.