Free PMI Project Management Professional (PMP) Practice Question

You are managing a software development project. In a status meeting, a team member suggests that some features could be delivered early, providing an immediate benefit to the client. However, delivering these features would require reallocating resources from a different task that is not on the critical path. What should you do next?

  • Assess the potential incremental value against project constraints before making a decision.

  • Ignore the suggestion since it was not part of the initial plan and proceed as scheduled.

  • Agree to the suggestion and reallocate resources immediately to deliver the extra value.

  • Adhere to the original project plan strictly, as deviations could lead to risks and delays.

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.