Free PMI Project Management Professional (PMP) Practice Question

You are managing a software development project using an agile methodology. During a sprint retrospective, the team identifies a need to change the way they handle user story prioritization. What is the best approach to execute this change?

  • Have the project manager handle the change without involving the team

  • Implement the change in the next sprint, allowing the team to adapt quickly

  • Implement the change during the current sprint, allowing no time to be wasted

  • Wait until the end of the project to implement the change as a secondary release

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.